Despite the cold (26 F not including wind chill) and the flurries, the concrete prep work did go on today.  The first thing the new work crew did was put plastic over the 2nd story exposed framing and start heating the place up with a torpedo heater.  Then they leveled out the clay and spread and tamped the rocks.  It really makes a difference in there, to not be up to your knees in mud and muck.  They are supposed to put plastic over the rocks, then a 1 1/2" foam board insulator then some type of mesh fabric.  Not sure I got that order right!  Concrete truck is supposed to arrive at 8:00 am tomorrow am.  The garage door installer is scheduled to arrive tomorrow or Wed (I can not remember...).  Hopefully, the electric panel board will go in this week as well.  The building crew is supposed to be back next Mon to finish the building.  Yeah!